Friday, May 2, 2014

Idaho Sand & Gravel is back

Construction resumes on Highway 75 widening project


By TERRY SMITH
Express Staff Writer

Crews operating backhoes and graders work this week on state Highway 75 near St. Luke’s Wood River hospital. The work is part of an Idaho Transportation Department highway widening project that extends south into the mid-valley. Photo by Willy Cook

   Idaho Sand & Gravel, the Jerome-based company contracted to widen a portion of state Highway 75 south of Ketchum, returned to the Wood River Valley this week to finish a job it started last year.
    The project is scheduled to be done this summer, Idaho Transportation Department Project Development Engineer Walter Burnside said at a meeting of the Blaine County Regional Transportation Committee on Thursday.
    However, ITD has already acknowledged that such may not be the case.
    “A lot of it depends on how the work goes,” ITD District 4 spokesman Nathan Jerke said in April. “They’ve still got more than half the roadway to construct.”
    Idaho Sand & Gravel, contracted by ITD to widen a 3.25-mile section of the highway for $9.44 million, is focusing initial work on completing the southbound traffic lane. Most of it was completed in 2013, but remaining to be done is the section of highway from the intersection of Hospital Drive north to the bridge over the Big Wood River.


A lot of it depends on how the work goes.
They’ve still got more than half the roadway to construct.”

Nathan Jerke
Idaho Transportation Department


    At some point, traffic passing through the construction zone on the old roadway from the bridge to Hospital Drive will have to be switched to the new southbound lane on the west side of the road. Burnside told the committee that the goal is to have that accomplished by the end of May.
    The project is officially known as the Timber Way to Big Wood River Bridge Project. Timber Way does not intersect Highway 75, but is located to the west and just north of East Fork Road. The bridge referred to is the one near St. Luke’s Wood River hospital.
    ITD issued its first construction update of the year on Wednesday. The construction updates are distributed by the department about every other week to local officials, the news media and other interested parties.
    In addition to work on the southbound lane, the update states that traffic may be reduced to one lane starting on May 7 while a pipe is installed across Hospital Drive South. Flaggers will be out to control traffic during the operation.
    Other upcoming work includes installation of curbs and gutters north of the Hospital Drive intersection beginning on May 12. Paving is expected to take place the week of May 19.
    The update states that work will also start soon for the northbound lane on the east side of the roadway. Initial work will involve installation of storm drainpipe and underground storm water settling ponds.
    Milling and excavation of the northbound lane is expected to begin after Memorial Day weekend.
    ITD also noted in the update that utility work will continue in some areas “throughout the project as necessary.”
    Once completed, the 3.25-mile section of highway will have two lanes in both directions and center turn lanes and deceleration lanes at key intersections.
    The project is the first phase of a 27-mile expansion plan for Highway 75 from Timmerman Junction north to Saddle Road in north Ketchum.
    Work on the second phase, which involves replacing the bridge near St. Luke’s and widening the highway to four lanes north to Elkhorn Road, is planned to begin in 2016.
    The remaining phases are still unfunded.




About Comments

Comments with content that seeks to incite or inflame may be removed.

Comments that are in ALL CAPS may be removed.

Comments that are off-topic or that include profanity or personal attacks, libelous or other inappropriate material may be removed from the site. Entries that are unsigned or contain signatures by someone other than the actual author may be removed. We will take steps to block users who violate any of our posting standards, terms of use or any other policies governing this site. Use of this system denotes full acceptance of these conditions. Please review the full rules governing commentaries and discussions. You are fully responsible for the content that you post.

The comments below are from the readers of mtexpress.com and in no way represent the views of Express Publishing, Inc.

You may flag individual comments. You may also report an inappropriate or offensive comment by clicking here.

Flagging Comments: Flagging a comment tells a site administrator that a comment is inappropriate. You can find the flag option by pointing the mouse over the comment and clicking the 'Flag' link.

Flagging a comment is only counted once per person, and you won't need to do it multiple times.

Proper Flagging Guidelines: Every site has a different commenting policy - be sure to review the policy for this site before flagging comments. In general these types of comments should be flagged:

  • Spam
  • Ones violating this site's commenting policy
  • Clearly unrelated
  • Personal attacks on others
Comments should not be flagged for:
  • Disagreeing with the content
  • Being in a dispute with the commenter

Popular Comment Threads



 Local Weather 
Search archives:


Copyright © 2014 Express Publishing Inc.   Terms of Use   Privacy Policy
All Rights reserved. Reproduction in whole or in part in any form or medium without express written permission of Express Publishing Inc. is prohibited. 

The Idaho Mountain Express is distributed free to residents and guests throughout the Sun Valley, Idaho resort area community. Subscribers to the Idaho Mountain Express will read these stories and others in this week's issue.